The scope of CCC certification for motor vehicles shall be in accordance with the requirements of the Implementing Rules for vehicles of category M, N and O (including complete vehicles and non-integrated vehicles). The certification according to the general safety standards eg GB 7258 "technical requirements for the safe operation of motor vehicles", For specific product inspection articles, please refer to the implementation rules of CNCA-C11-01: 2014 Automotive Annex 1 Type Test Projects and Standards.

1, How long does it take from the application to the receipt of the certificate?

90 days are set by law for cetification. According to experience, these sometimes take longer.

* it could result in a delay in processing:

if application documents are not complete,

if there are problems with testing in the Test Lab,

if there is a deviation in the audit.

Source: CCAP-C11-01: 2014 / A1 page 4, item 6.2

2, How often does factory audit take place?

Plant is classified after the initial audit in A, B, C, D.

A: Factory audit takes place once every 2 years.

B or C: Factory audit takes place once a year.

D: Factory audit takes place at least twice a year.

Source: CCAP-C11-01: 2014 / A1 Page 2, Point 4.2, CCAP-C11-01: 2014 / A1 Page 13, Point 10.2

3, how many audit days are there at the Inital Audit or the FU Audit?

Initial Audit: up to 10 man day per model series, depending of subparts certified

FI audit: up to 6 man day per model series

Source: CCAP-C11-01: 2014 / A1 page 9, clause 9.2.1.2,

CCAP-C11-01: 2014 / A1 page 14, item 10.3.2

4, how is the audit conducted?

Factory audit is performed according to IR CNCA-C11-01 Appendix 5

- Responsibility of quality manager: Appointment letter and service description (creation of control documents, management of change, complaint, CCC mark, CCC certificate status, etc.)

-Technical documentation: management of technical documents, control plan, product standard, product description of existing / new products, etc.

-Overview control: control of property, model and supplier of core material and core components, etc.

- Checking product compliance: running tests, final tests, etc.

Review of production process compliance: review of product structure, material and component, conformity of core production process, etc.

Product Check: Requalification Test

Change control: control of change request, etc.

Control of serious quality problems: customer complaint, recall, etc.

Source: IR CNCA-C11-01 Appendix 5

5, which application documents should be submitted to the initial audit?

  1. Application form
  2. License in copy-Questionário incluindo informações breves sobre a empresa, processo de produção, lista de instalações centrais de produção, lista dos principais instrumentos de teste, prova de marca registrada, etc.
  3. Car structure and technical parameters
  4. COP control plan
  5. Declaration: how is type, series defined
  6. Declaration: how is VIN defined
  7. Explanation: we distinguish the different types by external marking
  8. Declaration: Operating instructions in Chinese
  9. COC certificate
  10. Review
  11. Quality Manual
  12. Quality system certificates in copy
  13. Etc.

Source: CCAP-C11-01: 2014 / A1 Page 22-23 Appendix 1

6, how is Unit (technical unit) defined?

Step 1: Group car first after series defined by manufacturer

Step 2: Units are removed from the same series

It can not be defined as a unit if:

- Car types are not the same (M1 - up to 9 seater, M2 - from 10 seats, M3, N1, N2, N3, O1, O2, O3, O4), see below 8.1.1, 8.1.2, 8.1.3.

- car series is not equal

- position of the engine is not equal (front, middle, rear)

- fuel is not equal (gasoline, diesel, gas, electricity, etc. Hybrid "gasoline + electric" is considered as same unit as gasoline engine, hybrid "diesel + electric" is considered as same unit as diesel engine)

- Drive is not equal (four-wheel, non-four-wheel)

- Sum of the axis is not equal

- Etc.

Within one unit:

- Vehicle outside dimension limit: 20%, longest <= shortest x 1.2

- Limit axle position, wheelbase: 15%, longest <= shortest x 1.15

- Limit parameters (total weight, distribution of front and rear axle): 20%

- Etc.

6.1 M1

Same design platform, structure from part before B pillar similar (sedan, station wagon, convertible with hardtop, convertible with folding roof, etc.)

Limit within one unit: Engine KW: 30%, Displacement: 20%

6.2 M2, M3, N1, N2, N3

Limit value for engine KW: 50%, engine capacity: 50%

Limit within one unit: total weight: 20%

Source: IR CNCA-C11-01 Appendix 2

7. Which tests are performed according to which GB standard?

See CCAP-C11-01: 2014 / A1 page 29-45

8, List of key component and materials:

See CCAP-C11-01: 2014 / A1 page 22-23 Appendix 1 page 24-27

Notícias CCC

escopo de negócios para testes de laboratórios na China atualizado escopo de negócios para testes de laboratórios na China atualizado 2019-01-04 - de acordo com um anúncio recente, o seguinte negócio ...
Padrões 46 GB sob revisão Padrões 46 GB sob revisão 2018-12-30 - De acordo com uma recente imprensa divulgada pela Standardization ...
escopo de negócios de laboratórios de teste credenciados para produtos CCC atualizado escopo de negócios de laboratórios de teste credenciados para produtos CCC atualizado 2018-12-26 - de acordo com um anúncio recente da CNCA, escopo de negócios ...
Calendário de feriados 2019 da China anunciado Calendário de feriados 2019 da China anunciado 2018-12-23 - de acordo com um recente anúncio do General Office of ...
Catálogo China CCC atualizado Catálogo China CCC atualizado 2018-12-17 - De acordo com um recente anúncio conjunto da SAMR ("State ...
novos organismos de certificação CCC da China para produtos contra incêndios novos organismos de certificação CCC da China para produtos contra incêndios 2018-12-16 - de acordo com um anúncio atual da CNCA ("Certificação ...
27 New GB Standards lançado 27 New GB Standards lançado 2018-11-26 - De acordo com uma recente imprensa divulgada pela Standardization ...
7 New GB Standards lançado 7 New GB Standards lançado 2018-11-03 - De acordo com uma recente imprensa divulgada pela Administração do Estado ...
China Reforma do Sistema de Certificação Compulsória (CCC) China Reforma do Sistema de Certificação Compulsória (CCC) 2018-10-25 - Em outubro 22, 2018, Premier Li Keqiang presidiu o ...
Novos laboratórios de testes credenciados para produtos CCC 2018-10-16 - CNCA ("Administração de Certificação e Credenciamento da República Popular da China") ...

Suporte

Apoio

Você trabalha no seu ritmo. Você pode gerenciar seus projetos de forma independente através de nosso portal, bem como obter informações sobre suporte pessoal. Portanto, nos comprometemos com a oportunidade de projetar seus próprios processos

Administração Online

Administração on-line

Oferecemos-lhe a oportunidade de realizar o seu próprio processo de certificação, mas sem ter que renunciar ao know-how ou ao apoio de funcionários experientes. O sistema on-line é projetado para uma variedade de certificações e oferece listas de perguntas frequentes, além de formulários e tabelas prontas, além de um módulo para esclarecer questões abertas com um de nossos funcionários.

Certificação de mudança

Certificação de mudança

Em nosso tempo rápido, mudanças na vida empresarial são um acompanhamento constante. Pode ser esmagado muito rapidamente. Existem razões internas e externas para isso. O CS fornece uma visão geral da conformidade durante as alterações.

Cooperação

Cooperações

Nós só temos um tempo limitado e capacidade financeira, e queremos oferecer um serviço abrangente, as cooperações só fazem sentido entre as organizações relacionadas. Estes têm uma estrutura confiável, bem como uma boa harmonia interpessoal.

Ir para o início